» » » About Different S Curve Values?

About Different S Curve Values?

Hi everyone, hope all of you are doing great.
I have a question, please help me out with possible justification.
That, schedule percentage shows is the amount of work you have planned for a particular month. 
Now when I drive S-Curve from P6 it is showing different value.
For example.
One of the project I'm working, driven S-curve is showing 16% planned value upto December and when I go and schedule P6 on December 30 or 1 Jan it is giving 14.54% as my planned value.
I don't know why it's giving different values.
13.12.2020, 16:08 1 cevap 376 okunma 0
Bilgilendirme! Cevap ve yorum yazabilmeniz için sitemizde üye kaydınızın olması gerekmektedir.